Company outlines plan for 1,300-acre solar project in Barre, Shelby

By Tom Rivers, Editor Posted 21 December 2020 at 10:21 pm

Community Energy says construction of 200-megawatt Orleans Solar could start in 2022, be complete in 2023

This is the proposed layout for Orleans Solar in Barre and Shelby.

BARRE – A company wants to build Orleans Solar, a 200-megawatt solar energy project in the towns of Barre and Shelby.

Community Energy went over the project in an online forum this evening. The project would cover 1,300 acres, with about 75 percent in Barre and 25 percent in Shelby.

Community Energy expects it will complete the permitting process by the second quarter in 2022, with construction to commence in the third quarter of 2022. Interconnection to the grid would be complete in the third quarter 2023, with construction done the fourth quarter that year.

That was the timeframe presented by Joe Green, director of development for the company based near Philadelphia, Pa.

The layout of the project would be from east of East Shelby Road in Shelby, past Burns Road in Barre. The solar project is in a sparsely populated part of the two towns near the Iroquois National Wildlife Refuge. A main transmission line from National Grid runs through the project. Community Energy won’t need any battery storage facilities for the project, with the power going right into the grid, Green said.

Most of the land is currently used for corn and soybean farming. Community Energy is working with 10 landowners on the project.

Community Energy did the first and only large-scale solar project so far to make it through the Article 10 siting process for renewable energy in New York. Mohawk Solar in Montgomery County is a 95-megawatt project, less than half of what is proposed with Orleans Solar.

With Mohawk Solar, Community Energy is paying the taxing jurisdictions $300,000 annually, with 2 percent increases. That is $3,333 per megawatt the first year.

If Community Energy reaches a PILOT for payments to taxing jurisdictions at the same $3,333 level, the total revenue paid to the taxing jurisdictions would be about $667,000.

Green said the company wants to work on the PILOT agreement with the local government leaders in 2021. “We haven’t had those discussions yet,” he said about the PILOT.

The project should have 5-6 full-time equivalent employees. Construction is expected to be between $200 million to $250 million, Green said, with 170 construction workers on site for about six months.

The state is moving to a new siting process for large-scale renewable energy, from Article 10 to 94-C. James Muscato, an attorney assisting the company with the siting process, said 94-C should allow projects around the state to be sited “in a more uniform fashion.”

Community Energy needs to work with several state agencies and the host municipalities as part of the review.

“The project must be designed to avoid or minimize, to the maximum extent practicable, potentially significant adverse environmental impacts,” Muscato said.

The company needs to provide $200,000 in intervenor funds – $1,000 per megawatt – for the municipalities and community organizations to hire experts to review the application.

Community Energy is working to delineate wetlands and streams. The company will establish boundaries of all wetlands and streams on lands with the project, and will need to minimize impacts or avoid those areas.

It is also doing its avian studies in consultation with US Fish and Wildlife Service, NY Natural Heritage Program and the state Department of Environmental Conservation. The company has done multiple habitat evaluations and has identified northern harriers, short-eared owls and upland sandpipers.

The company will also be providing visual impact studies as part of the project with simulations throughout the 2-mile visual study area.

For more on Orleans Solar, click here.

County planners back extending solar moratorium in Barre

By Tom Rivers, Editor Posted 17 December 2020 at 7:34 pm

BARRE – The Orleans County Planning Board met this evening and recommended the Town of Barre extend a moratorium on applications for solar energy installation systems by another six months.

The town’s moratorium is to expire this month, said Tom Keeler, a member of both the county and Barre planning boards.

Barre wants more time to put a policy in place for battery storage systems for larger-scale solar projects.

Barre is looking at what other towns have done for regulated the battery storage systems for the projects, Keeler said.

The County Planning Board also voted on two other referrals from Barre:

• Barre Zoning Change – Expanding General Business District: The County Planning Board recommended the Town of Barre amend its zoning map to expand the B-General Business District along Route 98, within and south of Barre Center, Maple Street in Barre Center and West Lee Road to the west of Route 98.

The changes make the town’s zoning in line with the town’s comprehensive plan and will guide future development in the town, county planner said.

• Barre Zoning Change – Residential-1 to Agricultural Residential District: The County Planning Board supported Barre’s proposal to amend the zoning map to rezone the R-1 District to the AR District. This will be allow the town’s zoning map to be in line with the town’s comprehensive plan.

The majority of the R-1 District will change to Agricultural-Residential except for those along Route 98 from Route 31A south to West Barre Road, except for the existing Business District; and a small portion of Route 31A west, starting at the Light Industrial District.

The intention of the change is to “retain the small town atmosphere and rural character of Barre,” town officials said in the referral to the county.

Santa Express delivers presents in Barre

By Tom Rivers, Editor Posted 13 December 2020 at 3:16 pm

Provided photos

BARRE – The Barre Volunteer Fire Company took Santa on 28 stops around town today for the sixth annual Santa Express.

People dropped off gift-wrapped presents at the firehall and those gifts were then delivered by firefighters and Santa.

Santa and the Barre firefighters took Covid precautions on the tour today, by not allowing children on the fire truck or to sit on Santa’s lap. Santa wore a mask, delivered the presents and posed for photos with the kids who also wore masks.

The fire company wants to spread holiday cheer. The Santa Express also is a fundraiser for the fire company with families giving a suggested $30 donation for a visit from Santa.

Here are some more photos from the Santa Express:

Barre Lighted Tractor Parade proves a bright spot

By Tom Rivers, Editor Posted 12 December 2020 at 8:22 pm

Photos by Tom Rivers

BARRE – About 20 tractors and trucks were decorated in lights for the third annual Barre Lighted Tractor Parade. The procession started on East Barre Road at the Van Lieshout farm and headed north on Route 98 to the Barre Town Park.

This group of tractors includes one driven by Kurt Dudley in center.

Mike Van Lieshout lead off the tractor parade with a message, “A Barre Merry Christmas To All.” The event was organized by the Barre Betterment Committee.

These kids, the grandchildren of Richard Bennett, enjoy the ride with Frosty on a display for A.L. Bennett & Sons.

Shaw Farms in Byron joined the parade, which included trucks, tractors and smaller all-terrain vehicles.

Gallagher Hill Trucking in Albion had a lot of lights on their display.

A lineup of tractors is in the staging area at the Van Lieshout farm.

This farm offered a tribute to a Holstein cow.

This year’s parade included more spectators along the route than last year, when a near blizzard broke out. Today’s parade had a sprinkle of rain with temperatures at about 50 degrees. Many of the spectators watched from vehicles parked by the road with their windows down.

Santa made a joyful appearance in the parade.

Albion school accepts PILOT agreement from Heritage Wind

By Tom Rivers, Editor Posted 9 December 2020 at 8:20 pm

District could receive up to $201,600 in first year, plus another $50K in one-time payment

BARRE – The Albion Board of Education agreed to a payment in lieu of taxes agreement with the developers of Heritage Wind, a deal that would bring up to $201,600 in the first year, plus 2 percent in annual increases.

Apex Clean Energy, the developers of the project, also offered a $50,000 one-time payment to be paid within 15 days of when construction of the project is done. The company is proposing to build 33 turbines with a 5.6 megawatt capacity of 184.8 megawatts total.

The company has offered $9,000 per megawatt annually to be shared among taxing entities in a PILOT or community host agreement.

Barre has opted out of a PILOT and instead is trying to negotiate a host community agreement. That way Barre will get a majority of the revenue from Apex. With a PILOT, the money tends to be divvied up based on the tax rates of the municipalities. With that approach, the school district would get the largest percentage with Barre getting less than the school and county.

With the PILOT agreement, Albion would receive $1,091.91 per megawatt annually or $201,600. One of the 33 turbines also is proposed to be in the Oakfield-Alabama school district, which would receive $34.09 per megawatt or $6,300 annually.

Orleans County would receive $1,125 per megawatt for $207,900 in the first year, with 2 percent annual increases to follow.

Heritage also agreed to $50,000 to the school district for a one-time “Heritage Wind Renewables Ecology, Clean Energy, and Sustainability Scholarship and Education Support Fund.” The money is to be spent at the discretion of the district. It could be used for scholarships, science fairs, student research projects, financial support for faculty in renewable energy field, a STEM lab or “however the district deems fit.” The $50,000 is to be paid within 15 days after completion of the project.

The Board of Education accepted the terms of the PILOT on Monday, with the understanding the BOE isn’t stating support or opposition for the project. That decision will be left to the town and the state, the BOE said.

“Approving these resolutions does not mean that the district is in favor or against the construction of the wind mills,” the BOE stated in its resolution. “The district has made it very clear that this is a decision to be made by the people in the Town of Barre and the State of New York. These are just procedural items necessary in order to be included in the distribution of funds if this project does move forward.”

The Albion school district had a tax levy of $8,449,094 for the 2020-21 school year. The $201,600 would represent 2.4 percent of the school taxes.

For the county, the tax levy in 2021 is $18,309,497. The $207,900 for the county represents 1.1 percent of the county taxes.

The revenue for Barre would make a much bigger difference in the town taxes. Barre’s 2021 budget calls for a tax levy of $1,108,566.

Apex has offered the local taxing jurisdictions $9,000 per megawatt annually. If the project is built as proposed at 184.8 megawatts that would be $1,663,200 in total annual revenue.

The PILOT includes first year payments of $207,900 for the county, $201,600 for the Albion school district and $6,300 for Oakfield-Alabama – $415,800 total. Subtracting that from $1,663,200 might leave $1,247,400 for Barre, which would more than wipe out the town taxes. (The terms for the Barre host community agreement haven’t been publicly disclosed.)

Heritage Wind officials will discuss the proposed project for Barre during a virtual public meeting from 6 to 7:30 p.m. on Thursday. Click here for more information.

Barre Lighted Tractor Parade will head down 98 on Saturday

File photos by Tom Rivers: Lamb Farms in Oakfield had a patriotic display during last year’s Barre Lighted Tractor Parade. This year’s event will be on Saturday at 5:30 p.m.

By Tom Rivers, Editor Posted 8 December 2020 at 10:12 am

BARRE – The third annual Barre Lighted Tractor Parade is scheduled for 5:30 p.m. on Saturday.

Tractors should show up on East Barre Road by 5:15 p.m. They will then head north on Route 98 to the Barre Town Park. No RSVPs are needed in the event planned by the Barre Betterment Committee.

Last year the event went on despite heavy snow. This year there is a pandemic. Organizers urge spectators to adhere to social distancing and wear facial coverings.

About a dozen tractors participated in the parade on Dec. 14 last year during heavy snow. This year the forecast shows a good chance for rain, but no snow during the event.

Barre holding public hearing today on proposed ordinance for wind energy

By Tom Rivers, Editor Posted 4 December 2020 at 9:53 am

BARRE – The Town of Barre will hold a public hearing today at 6 p.m. for its proposed ordinance on wind energy projects.

The Town Hall is closed to the public due to Covid-19 concerns. People can be part of the hearing by calling (585) 589-5100, enter 5, and then 4321#.

The hearing will also be live on YouTube by clicking here.

Comments and questions can be texted to 588-590-6069, emailed to spogue@townofbarreny.com, the right side of YouTube, or the drop box to the left of the front door.

All comments must be in by the close of business on Dec. 14.  Comments and questions with responses will be posted on the town website.

Photos of Trunk or Treat at Barre Town Park

By Tom Rivers, Editor Posted 31 October 2020 at 7:08 pm

Provided photos

BARRE – The Barre Betterment Committee hosted a safe Trunk or Treat at the Barre Town Park today with about 100 kids coming out from 2 to 4 p.m.

This is the first time the Betterment Committee hosted the event. There were 12 trunks with candy and treats.

Barre will discuss zoning changes for turbines on Oct. 14

By Tom Rivers, Editor Posted 8 October 2020 at 9:04 am

BARRE – The Barre Town Board is reinstating its workshop for 5 p.n. on Oct. 14 at the Town Hall to discuss proposed changes in for wind energy regulations.

The town scheduled a public hearing on Sept. 28 about the changes but cancelled that so neighboring towns and counties could be notified that Barre was considering changes in the zoning.

Barre is expected to set a new date for the public hearing at the Oct. 14 meeting.

Among the revisions proposed include increasing the maximum height of a wind turbine, from tip height, to 700 feet. The town currently sets the limit at 500 feet.

Apex Clean Energy is proposing wind turbines that would be a maximum 680 feet high as part of a 33-turbine Heritage Wind project in Barre.

The zoning amendments also would set the setbacks from property lines to be at least 1.5 times the tip height of a turbine, and that is for non-participating land owners or those without leases for a turbine.

The zoning changes also would revise standards for noise levels for wind turbines, shadow flicker and construction hours. The town also is looking to add requirements for aircraft detection lighting and for decommissioning of the turbines.

The meeting on Oct. 14 will be limited to nine individuals or resident groups (husband and wife) to allow for social distancing, said Sean Pogue, the Barre town supervisor.

People can also call (585) 589-5100 to listen in on the discussion. Callers should press 5 and when asked then press 4321.

Return to top

Barre cancels public hearing on Wednesday for zoning changes on wind turbines

By Tom Rivers, Editor Posted 28 September 2020 at 3:53 pm

BARRE — The town has canceled a public hearing scheduled for 6:30 p.m. Wednesday at the Barre town highway garage, 14317 West Barre Rd.

Town Supervisor Sean Pogue said the hearing will instead be in late October. That date will be set at the Oct. 14 Town Board meeting.

Pogue said the hearing needed to be pushed back so neighboring towns and counties could be notified that Barre was considering changes in the zoning.

Among the revisions proposed include increasing the maximum height of a wind turbine, from tip height, to 700 feet. The town currently sets the limit at 500 feet.

Apex Clean Energy is proposing wind turbines that would be a maximum 680 feet high as part of a 33-turbine Heritage Wind project in Barre.

The zoning amendments also would set the setbacks from property lines to be at least 1.5 times the tip height of a turbine, and that is for non-participating land owners or those without leases for a turbine.

The zoning changes also would revise standards for noise levels for wind turbines, shadow flicker and construction hours.

The town also is looking to add requirements for aircraft detection lighting and for decommissioning of the turbines.

Return to top