Large concrete pieces set in place for new Phipps Road bridge in Albion

By Tom Rivers, Editor Posted 20 November 2026 at 8:36 am

Photos by Tom Rivers

ALBION – A crane from Clark Rigging moves a 38,900-pound precast concrete piece for a new bridge over Otter Creek on Phipps Road in Albion.

There were five of the concrete pieces set into place on Thursday. The new bridge will be 25 feet long, where the previous one was 19.5 feet. That will allow for more flow in the creek during peak storm events.

The previous bridge was washing away from the creek. The bridge was closed on Sept. 9, 2022 after an inspection showed the steel high-beam supports were rotted.

Keeler Construction is general contractor for the project, after submitting the low bid of $992,851.

The new bridge is close to being done. Keeler also will be installing the bridge header and wing walls, doing back fill, putting on binder for the top and installing guard rails. The bridge should be open in early December, said Mike Neidert, the Albion highway superintendent.

A final topcoat will be added in the spring.

Neidert and Albion Town Board secured a state $1.038 million grant through the Bridge NY program that is covering most of the cost for the new structure.

Mike Neidert, the Albion town highway superintendent, stands on the west side of the bridge close to Eagle Harbor Road. Underneath are culvert pipes which are being used temporarily to keep the creek flowing during the construction project.

Here are some additional photos from Thursday: