Keeler Construction will replace Portage Road bridge in Ridgeway

By Tom Rivers, Editor Posted 29 June 2018 at 7:50 am

RIDGEWAY – Keeler Construction of Albion is expected to start construction in about three weeks on the replacement of the Portage Road bridge in the Town of Ridgeway.

The Orleans County Legislature on May 30 accepted Keeler’s bid of $588,821 to replace the bridge. The project should be complete by November, said Jerry Gray, the county’s highway superintendent.

The total project costs with engineering, inspection and other expenses is estimated at $869,000. This is a Bridge NY project with the county paying 5 percent of the costs or $43,450.

The county also expects to soon seek bids to replace a culvert on South Holley Road in Clarendon, a construction project that could extend into the spring, Gray said.

The county also is working to replace a bridge on the Monroe-Orleans Countyline Road near the golf course. The county is waiting on state approval for the project, which Gray said will probably get started next spring.