Holley village accepts $2.6 million bid for sidewalks, waterlines

By Tom Rivers, Editor Posted 12 February 2020 at 8:23 am

HOLLEY – The Holley Village Board accepted a $2,556,000 construction bid from a contractor on Tuesday to replace sidewalks and water lines in the village. Most of the project is along Route 237 and the northeast section of the village.

Mark Cerrone, Inc. of Niagara Falls submitted the lowest bid for the project. Grants will cover the majority of the costs. Holley is responsible for 20 percent of the sidewalk work and 40 percent of the waterlines. The village will put in some sidewalks and waterlines as part of its share for the project, which has a total cost of about $4.5 million, said Mayor Brian Sorochty.

The village has been approved for a $1,780,000 federal TAP grant (Transportation Alternatives Program) to construct curbs and sidewalks that are compliant with the Americans with Disabilities Act. The grant will allow the village to replace about one-third of the sidewalks in the village.

That includes sidewalk along Rt. 237 – both north and south of Rt. 31 to the village limits (from the water tower to the elementary school), as well as both sides of Geddes Street from Van Buren to Route 31, both sides of Perry Street, both sides of Morgan Street and the west side of East Avenue.

Holley also was awarded nearly $1.3 million from the state for upgrades to the water system through the Water Infrastructure Improvement Act, as well as the Intermunicipal Water Infrastructure Grants Program.

The waterline project includes 5,800 linear feet, just over a mile, and involves replacing 4- to 8-inch water mains with 8- to 12-inch water mains.

That project includes portions of South Main (from the water tower to Batavia Street), South Main from Jackson Street to West Albion Street, water service transfers only along North Main from West Albion Street to the high school, the northerly side of Geddes Street from Van Buren Street to Public Square, along with connections to existing waterlines at ends and side streets.

Cerrone is expected to get started on the project soon and be complete in about a year before the state starts a milling and paving project on Route 237.