Holley school board reviews $22.9 million capital project, classroom learning initiatives

A rendering presented to the board showed proposed changes to the front entrance canopy at the middle-high school.
By Isabella Zasa, staff writer
HOLLEY – The Holley Central School District Board of Education received an update Monday night on its voter-approved $22.9 million capital project, including auditorium renovations, building improvements and construction timelines.
Steve Shchurowsky of Young + Wright Architectural presented the update. Voters approved the project in March 2026 by a vote of 207-60, following a districtwide facilities evaluation completed in 2024.
The project is being completed in two phases, with the first focused on renovations to the middle-high school auditorium. The district received 22 bids for the work in August, totaling $3,175,182, which was in line with the project budget, said Shchurowsky.

Photos by Isabella Zasa: Steve Shchurowsky of Young + Wright Architectural presents an update on the district’s $22.9 million capital project to the Holley Board of Education during its monthly meeting Monday night.
“Turnout for a job of that size is fantastic,” Shchurowsky said.
The auditorium renovations will focus on the stage, rigging, curtains and lighting. The project will also include painting, replacing wall panels and improving acoustic treatments to enhance the space.
Construction is expected to begin around Dec. 28. The auditorium will remain available for district use through the holiday season, with work scheduled to continue through August 2027. The space is expected to be returned to the district before the start of the 2027-28 school year.
Temporary partitions will be installed to separate the construction area, and contractors will use a designated entrance at the rear of the building to limit movement through school hallways. The district has also designated storage areas and restrooms for contractor use.
Board President Tracy Van Ameron raised concerns about construction noise near the music hall and gymnasium. A Turner Construction representative said the initial steel work could be among the loudest portions of the project but could be scheduled to minimize classroom disruptions. Shchurowsky said welding is not anticipated during the school day because the connections are expected to be bolted, although some steel cutting may be necessary. Contractors will work in an isolated area and access the auditorium through the rear loading dock to further limit disruptions.
The second phase is scheduled to be submitted to the state this week, with approval targeted for early 2027. The district plans to bid the work in the spring, with construction taking place in 2027 and 2028. Heavier construction is expected in 2028.
Shchurowsky said the design process has involved collaboration with district staff and committees, particularly on restroom renovations and the middle-high school entrance.
“Designs have been collaborative, and the staff has been fantastic to work with,” Shchurowsky said. “It’s your space. We want to make sure you guys get what you want out of it.”
Planned improvements at the elementary and middle-high school include gymnasium renovations, window replacements and restroom upgrades.
Gymnasium work will include new flooring or refinishing existing floors with school logos, new lighting and air conditioning.

This rendering shows planned gymnasium renovations at the middle-high school and elementary school.
Windows throughout much of both buildings will be replaced, along with new roller shades and window sills. At the elementary school, the library will receive a new circulation desk, lighting and replacement millwork.
Restroom renovations will include new fixtures, becoming fully ADA compliant and replacing piping back to the main lines as much as possible to address drainage concerns and prevent backups. Designs also incorporate privacy measures, including mirror placement to prevent visibility into restrooms from hallways.
At the middle-high school, the existing entrance canopy will be removed and replaced with a new design featuring a tapered roofline, brighter exterior lighting and improved visibility underneath.
Additional improvements include parking lot repaving, plumbing upgrades at the transportation building, fiber infrastructure and security camera improvements across the campuses, and preparations for a restroom trailer near the athletic fields.

This slide shows how the capital project funding will be divvied up among district properties.
Shchurowsky said current estimates indicate the project could come in under its original budget, potentially allowing additional work to be included as bid alternates. However, the final scope will depend on bid prices.
Potential additions include additional window replacements, air conditioning, interior ceiling and flooring renovations, fire alarm upgrades and potable water service near the stadium.
The district also completed bidding for its 2026-27 capital outlay project, which involves replacing and infilling skylights at the elementary school. Shchurowsky said the district awarded the work to a contractor, but the number of skylights exceeded what could be completed within the $100,000 project budget. The remaining work may be incorporated into the larger capital project as an alternate.
In addition to the facilities update, Brendan Keiser, director of teaching and learning, outlined the district’s professional learning focus on inquiry-based learning and authentic assessments.
The initiative aims to shift students from being recipients of information to active participants in their education by encouraging them to develop questions, conduct research, draw conclusions and apply their knowledge to real-world situations.

Brendan Keiser, director of teaching & learning, gives a presentation on Inquiry Based Learning & Authentic Assessments.
“This year’s big question is: How do we design learning where students act as thinkers, investigators, creators and communicators, rather than recipients of information?” Keiser said.
Keiser explained that inquiry-based learning involves students developing essential questions, conducting research and building new understandings to answer questions, solve problems or support a position. Students may then present their findings to an audience or take action based on what they learned.
Authentic assessments, meanwhile, engage students in real-world problems or tasks, often requiring them to create something for an audience with an interest in or connection to their work.
The approach aligns with New York state’s Portrait of a Graduate, which identifies six attributes students should demonstrate before graduation: academically prepared, creative innovator, critical thinker, effective communicator, global citizen, and reflective and future focused. The district also has its own 10 Portraits of a Graduate competencies outlined in its strategic plan.
Keiser said traditional assessments, such as multiple-choice tests, may not adequately measure skills such as creativity and innovation. The district is encouraging teachers to provide opportunities for students to demonstrate their learning through research, collaboration, reflection and public presentations.
One example is the district’s senior capstone program, in which students present yearlong research projects to community members. Keiser described it as one of the district’s “crown jewels,” noting that students must demonstrate their understanding to an audience beyond the classroom.
The district has begun discussing how students might demonstrate the graduate attributes. During an October staff development day, faculty were asked to identify learning tasks that could provide evidence of the attributes and consider how those tasks might be assessed.
Middle-High School Principal Matt Feldman said the district is encouraging teachers to begin with manageable changes, such as replacing one question on a traditional benchmark assessment with an authentic task, rather than redesigning an entire assessment.
A formal assessment framework has not yet been established. When asked whether the district had developed a system to track which assessments measure specific attributes and how often students should demonstrate them, Keiser said, “The answer is no.”
He said he had raised the question with the state, which indicated that more detailed requirements would come further down the road.
The district also is piloting the ACT WorkKeys assessment this school year with students in grades 10-12. The national assessment measures career readiness and workplace skills. Depending on their scores, students may earn a National Career Readiness Certificate that can provide employers with evidence of those skills. Keiser clarified that WorkKeys is not a graduation requirement.
Feldman said the pilot is part of the district’s broader effort to ensure students feel prepared for life after high school. The district recently surveyed graduates from the classes of 2022 through 2026 to learn whether they felt adequately prepared after graduation and identify areas where additional support may be needed.
Student Ex-Officio members also shared updates on recent activities and educational opportunities.

Mya Gonzalez, student ex-officio member, gives the Board of Education an update on recent student activities during Monday’s meeting.
Mya Gonzalez reported that approximately 73 students attended the middle school dance, which was rescheduled to avoid conflicts with homecoming activities. She also discussed a visit to St. John Fisher University, where students learned about academic programs and had opportunities to ask questions.
Aidan Kelley shared highlights from a trip to SUNY Brockport, where students in college-level U.S. history and English classes learned about research databases and practiced using them for current assignments.
Board President Tracy Van Ameron praised the students for sharing their experiences and enthusiasm.
“It’s been a great thing to bring in these students,” Van Ameron said. “You guys are so excited about what you’re talking about, and I absolutely love hearing from you.”