Construction underway for pedestrian bridge, sidewalks on Maple Ridge in Medina
Photos by Tom Rivers
MEDINA – Construction has started on a new pedestrian bridge in Medina that will cross the Oak Orchard Creek.
RJT Construction Services in Rochester is the contractor for the project on Maple Ridge Road (Route 31A) in Medina. This area also will get about 2,000 feet of new sidewalks on the north side of the road.
The Medina Village Board on March 23 approved the $837,448 bid by RJT Construction Services to install the bridge and sidewalks. RJT was the lowest of four bidders when the bids were opened on Feb. 18.
The section of Maple Ridge Road by the creek has become busier with a housing development, several new businesses and also the GCC campus center. There are also about 200 available acres in the area being promoted for development by the EDA. (In this photo, the Mariachi de Oro Mexican restaurant is shown in the background.)
The new bridge and sidewalks have been several years in the waiting. The village in 2021 was awarded a $1,094,196 grant to construct the bridge and sidewalks as part of a multi-use path for pedestrians and bicycles. The funding was awarded by the state through a federal Transportation Alternatives Program (TAP) grant.
That is covering 80 percent of the project. The remaining 20 percent will be paid locally from the village ($55,000), Town of Shelby ($130,000) and Orleans County ($97,500).
In addition to the construction bid, the village has approved paying Barton & Loguidice $166,300 for construction services and inspections.