Albion bridge reopening pushed back from Dec. 26

By Tom Rivers, Editor Posted 19 December 2024 at 8:26 pm

ALBION – A day after announcing the Albion Main Street lift bridge was on target to reopen on Dec. 26, the reopening has been pushed back slightly.

Village Trustee Joyce Riley said she was notified today by the state Department of Transportation the bridge won’t be ready Dec. 26, but should open very soon.

The DOT and village will wait until the reopening is certain before putting out a date.

The bridge has been closed to traffic since Nov. 14, 2022. When it closed, the DOT estimated it would reopen in 18 months or the spring of 2024.

But there have been delays in getting materials for the project, pushing the completion back.

The bridge was originally built in 1914. It is one of 16 lift bridges on the Erie Canal, and one of seven in Orleans County.