Albion approves $19 million in school construction bids

By Tom Rivers, Editor Posted 7 February 2023 at 10:44 am

New turf football field among first projects, expected to be ready in fall

Photo by Tom Rivers: The end of the Albion football field is shown last week. The grass field will become turf in a project expected to be ready in time for the fall football season.

ALBION – The Board of Education on Monday evening unanimously approved eight construction bids totaling $19,300,000.

Another bid for $2.6 million is expected to be approved next month, bringing the total to $21.9 million.

That is well in budget and leaves a balance of $1,084,507 in contingencies, said Kevin Donaghue, executive vice president Campus Construction Management which is assisting the district in the bid preparation and oversight of the project.

School district residents on Dec. 14, 2021 approved the $26.69 million capital project that includes all three schools, as well as the bus garage, and new synthetic playing surfaces for football, soccer and softball.

After a design phase for the project and review and approval by the state Education Department, the project went out to bid to contractors. The bids were opened last week and on Monday the board gave its approval, with one more contract needing additional review.

“The big picture is the project is right on budget,” Donaghue told the Board of Education.

The bids accepted on Monday include:

  • Site work – $6,295,082 by Diehl Development
  • General Trades – $5,441,000 by Javen Construction
  • Mechanical – $2,797,700 by T. Bell
  • Plumbing – $1,636,300 by Blackmon Farrell
  • Playground equipment – $257,027 by GameTime
  • Scoreboards – $124,725 by Toth
  • BMS (Building Management System) Controls – $339,068 by Day

Day is also the low bidder for access controls at $2,596,942 that is expected to be approved at next month’s meeting. That system will allow badges to lock and unlock doors, and can do a district-wide lockdown of all classroom doors.

Contractors will soon be a presence on campus with most of the work happening after school.

The first projects will upgrades to the district officer, with the district office staff moving to the E wing of the elementary school during the work at the district office.

Contractors also will be pushing to replace the grass field at the football stadium with turf. That effort is expected to start in April with a push to be done in time for the football season in late August-September.

The softball field and varsity soccer also will get turf fields. That will start this year but isn’t expected to be done until 2024. The varsity field is expected to be available this upcoming season, Donaghue said.

He went over the construction schedule during Monday’s board meeting. The schedule includes:

• Site Work – In 2023 the work includes the football field replacement, track resurfacing, multi-purpose field replacement (softball and soccer – starting June 1, 2023 and ending July 15, 2024), elementary school hot water service line, elementary school drop-off loop and sidewalks, elementary school playground fence replacement and high school hot water service line.

In 2024, the site work includes middle school hot water service line, tennis court replacement, middle school drop-off loop reconstruction, concrete sidewalk replacements, playground replacement at middle school, baseball field drainage improvements, JV softball field drainage improvements.

• Construction at elementary school – In 2023, district office renovation, classroom doors and plumbing fixtures at E wing (Nov. 6 to Dec. 1), classroom doors and plumbing fixtures at D wing (Dec. 11 to Jan. 5), crawl space plumbing and hot water heaters, EIFS replacement, carbon monoxide detectors/fire alarm, and electrical abatement and replacements.

In 2024, classroom doors and plumbing fixtures at C wing (Jan. 1 to Feb. 9), classroom doors and plumbing fixtures at B wing (Feb. 19 to March 15), classroom doors and plumbing fixtures at A wing (March 25 to April 19) and classroom doors and plumbing fixtures at G wing (April 29 to May 24), emergency generator replacement, doors/hardware/security enhancements, main office windows and fire shutter, and gymnasium folding partition replacement.

• Construction at middle school (basement) – In 2023, pool deck structural repairs, boiler room abatement and demolition, boiler room plumbing renovations, ad pool pumps.

In 2024, electrical room A/C and auditorium A/C.

• Construction at middle school (first floor) – In 2023, domestic hot water repairs, replace insulated window panels, gymnasium renovations, pool lighting and locker room renovation, replace ANSUL system, exhaust fan and relief air work, flooring abatement, flooring installation, carbon monoxide detectors and fire alarm, and electrical service component replacements.

In 2024, doors/hardware/security enhancements and auditorium AC.

• Construction at middle school (second floor) – In 2023, exhaust fan and relief air work, replace insulated window panels, flooring abatement, and flooring installation.

In 2024, convert lockers into storage rooms, electrical room A/C, auditorium A/C, and doors/hardware/security enhancements.

• Construction at middle school (third floor) – In 2023, exhaust fan and relief air work.

In 2024, doors/hardware/security enhancements.

• Construction at high school (first floor) – In 2023, library door reconstruction, window lintel replacements, domestic hot water heaters and carbon monoxide detectors and fire alarm.

In 2024, replace lockers (with wider units), doors/hardware/security upgrades, gym renovations and gym locker room renovations.

• Construction at high school (second floor) – In 2023, library door reconstruction, window lintel replacements, domestic hot water heaters, and carbon monoxide detectors and fire alarm.

In 2024, replace lockers, doors/hardware/security upgrades, gym renovations, gym locker room renovations, gym HVAC abatement and demo, gym HVAC installation.