Tree-clearing to start next week for wind turbine project in Barre
Apex will focus on site work in 2026 before 28 turbines constructed next year
BARRE – The first phase of construction is expected to start next week for a high-profile project that has been 10 years in the making.
Apex Clean Energy will start clearing about 30 acres of trees next week in Barre. Apex has hired Ironwood Heavy Highway in Rochester for the job of clearing trees. Ironwood is expected to start cutting down trees on Jan. 19. The job should take a few weeks with work limited to between 7 a.m. and 8 p.m., said Carmen O’Keefe, the director of development, and Brian O’Shea, director of public of public engagement for Apex Clean Energy.
Apex is owner and developer of the Heritage Wind project in Barre, which will have the capacity to produce 126 megawatts of electricity.
The tree clearing is limited to no later than March 31 due to the presence of federally listed bats.
There will be a full mobilization of about 200 construction workers in the community in May or June to work on installing access roads, turbine foundations and other site work, including construction of turn radiuses for the delivering of the turbine components.
The Heritage Wind project will have 28 turbines, and the turbines will be constructed in 2027 with the project expected to be operational in late 2027, O’Shea said. The turbines will be more than 600 feet high.
The project also includes 10.5 miles of access roads, one permanent meteorological tower, 25.2 miles of collection lines, a temporary construction laydown yard of approximately 13.9 acres, a temporary concrete batch plant (if needed), parking for construction workers, an operations and maintenance facility with two buildings totaling about 4,000 square feet, and one aircraft detection lighting system tower.
For maps and more details of the project, click here.
Once the project is operational, Apex will pay $9,000 per megawatt to local municipalities or $1,134,000 in the first year, with a 2 percent increase after that over 25 years.
Barre gets 75 percent of the money as part of a Host Community Agreement. The $6,750 per megawatt totals $850,000.
The remaining 25 percent or $2,250 per megawatt is evenly split by the school district and county. That is $140,175 each.
In addition, Heritage Wind will be paying $4.575 million administrative fees to the Orleans Economic Development Agency for administering the PILOT with the school district and county.
The project also will save the average Barre household $150 annually in energy bills through the first ten years of the project’s operations through NYSERDA’s Host Community Benefit Program, O’Shea said.









